68 000 Seats, 2 300 Workers, 1 New Green Point Stadium

We dig up some enlightening facts and figures about the new Green Point Stadium for the 2010 FIFA Soccer World Cup


What’s got a price tag of R4.5 billion, will take 32 months to complete, is the height of a 15-storey building and will play a sizeable part in hosting by far the greatest soccer spectacle South Africa has ever seen? The new Green Point Stadium!

Construction is racing ahead at this 2010 World Cup stadium in Cape Town, and the forecast is that it will be completed by December 2009. We dug a little deeper to bring you some interesting facts:

Facts about the 2010 Green Point Stadium:

About the construction project:

Net construction value: R4.5 billion Project start: 26 March 2007 Practical completion: 14 December 2009 Overall duration: 32 Months Staff employed at peak: 300 Trade labour employed at peak: 2 300 Cranes at peak: 21 Project agents: 10


About the finished stadium:

There will be 68 000 seats (including 13 000 temporary) and it will host six first round matches, one second round, one quarter-final and one semi-final.

The stadium’s footprint is equivalent to six city blocks and it is 50m tall (same as a 15-storey building), and the dimensions of the field area will be 290m x 265m x 48m.

There will be 250 VIP suites, basement parking for 1200 cars and 16 lifts throughout the stadium, as well as a 1 800 square metre conference hall.

Provision will be made for 120 wheelchairs, with additional wheelchair positions / removable seats for accompanying families.

The design for the 2010 Green Point Stadium uses natural light for ambience and to save energy; the façade is covered with an open mesh fabric that plays with the natural light.

The Stadium’s roof line was designed to be as low as functionally possible as to ensure that views around the stadium remained protected. Ideally, the designers would have liked to dig the stadium deeper into the ground so that all visiting spectators would flow into a bowl in the earth.

However, the stadium could not be sunk into the ground as the hard rock under Green Point Common would mean that the builders would have to blast out the rock for a period of two years, which was not feasible due to time constraints.

The roof of the stadium is based on the design of a bicycle wheel which provides a perfect example and system for a roo

Partly Cloudy
21°C11°C
Thursday02. Sep 2010 | 18:00
Antiques 1The V&A Waterfront Antiques Fair

It’s all about things old …

Capetown MagazineValentines Day Sunset Hike

Bring that some one special for a sunset to remember

Awol & BEN tours 4Peninsula Township Insights by the ...

Extraordinary bicycle tour brings Xhosa customs to life in Masiphumelele

kite festival 2010 girls frogOctober Events Calendar

From Kites and Roses,  to wine in the townships, to rocking Daisies

lourensford 9Touring the Wine Estates of Somerset ...

Visit wine estates on the Helderberg slopes near Somerset West

Capetown MagazineClub Newlands Sleepover

Experience the stadium like never before...

minstrel carnival cape townJanuary Event Calendar Cape Town & ...

The year begins with pumping events in January in the Mother City

Bike and saddle 9See, smell and feel Cape Town by bike

A bicycle-ride through Cape Town gives you the real experience

TRIVIA

image description

WeatherGiveawaysTravel Tips2010 World Cup